STATUS A, B, C & D | What Do They Mean... - Constructandcommission.com (2024)

Within a construction project and the commissioning process, documents [technical, drawing, method statement, etc.] that are utilized for conveying detailed information from or to the manufacturers, site teams, design, and commissioning teams will need to be issued for approval, reviewed, and provided a Status A, B, C, D from the client team.

This is to accept that, what is being provided is in line with project/design and contract requirements, for works to commence.

Table of Contents

Status, Review Process, and Types of Documents…

Below details the Status, Review Process, and Types of Documents that would generally need to be provided for comment/approval.

We generally have come across two different types of status on projects:

  • The first is where a Status of A, B, C is given
  • The second is where a Status of A, B, C & D is given

Whilst the two look similar there are slight differences.

The below table details the status of documentation and what they can mean on a project. As can be seen the Status D, is basically included to provide the reviewer with an ability to fully reject a document. It usually means that the submitted document does not meet what the title is, is completely inadequate to explain or describe what its intended for, or there is significant information and data missing.

StatusStatus A,B,CStatus A,B,C,D
ADocument reviewed

No comments

Works can commence

Document reviewed

No comments

Works can commence

BDocument reviewed comments noted

Works can commence taking onboard comments

Document reviewed comments noted

Works can commence taking onboard comments

CDocument reviewed comments noted

No works can be allowed to commence

Revise and reissue document for approval

Document reviewed comments noted

No works can be allowed to commence

Revise and reissue document for approval

Dn/aDocument reviewed

Not meet any requirements of the project

Fully rejected

No works can be allowed to commence

Revise and reissue document for approval

What is the Review Process?

The review process is usually pretty straight forward as noted below:

  • General Contractor / Main Contractor and their teams create the documentation / information.
  • Internal Review conducted by Main Contractor Engineers.
  • If internal review ok, then issue to *client team via email or some form of electronic platform such as Aconex / Asite / Procore etc.
  • Client team review and provide comment / approval based upon Technical, Installation, Commissioning & Maintainability.

*The Client Team would consist of the Client, Project Manager, Designer, Commissioning Consultant, Facilities Team etc. [if on board early enough].

What types of documents are usually issued for review?

Which documents will require to be issued for approval, will generally be dictated by the specific project/contract documents.

As an outline, the documents as listed in our articles below would usually be required, relating to the commissioning process:

  • COMMISSIONING DOCUMENTS | 368 of them listed here
  • CONSTRUCTION DOCUMENTS | Explained

Material/Technical Submissions

These are generally focused upon items of equipment and materials that will be selected and manufactured to meet the design requirements as set out in the project specifications. The materials and equipment can range from details of pipework/cables to generator and chillers.

Material Submissions are usually issued by the general contractor / main contractor for approval by the design team. The commissioning manager should also support reviewing these documents.

Drawings

The designer will usually issue a full set of design drawings to the project – these will detail the expectations relating to what should be installed where, sizes, flow rates, and any simple control logic, etc. The general contractor / main contractor would take these drawings, fully coordinate the services, and produce ‘shop drawings’ / ‘working drawings’.

These shop/working drawings should be reviewed and commented upon by the project team [designer, commissioning consultant].

Testing Procedures

Testing procedures should be developed by the General Contractor / Main Contractor for the future commissioning works – these will range from early testing requirements such as Weld / Pressure Testing all the way through to the final building-integrated testing.

These testing procedures should be reviewed and commented upon by the commissioning consultant, coordinating with other team members such as the designer and facilities staff.

Testing Sequence and Programme

The expected testing program and sequence of works should generally be developed by the general contractor / main contractor.

This testing program/sequence should be reviewed and commented upon by the commissioning consultant, coordinating with other team members such as the designer and facilities staff.

Related Articles

Go To Article

THE COMMISSIONING TEAM | Example Organigram for each stage

Go To Article

CRAC Unit vs CRAH Unit | What’s the difference?

Go To Article

BASIS OF DESIGN | [BoD] How to Write with download

Go To Article

HOW TO WRITE | A Method Statement with download

Go To Article

ASHRAE | Who are they…

Go To Article

STATUS A, B, C & D | What Do They Mean... - Constructandcommission.com (1)

⬛ Latest Articles

Go To Article

DATA CENTER COMMISSIONING | What is it?

Go To Article

TIER V Platinum Data Center | What is it?

Go To Article

BUILDING SYSTEMS MANUAL | How to Write One with Roles

Go To Article

SPRINKLER PIPEWORK | Pre-Commissioning Checklist

Go To Article

⬛ Author

If you would like to know more about the author, here is my Personal Linkedin Account

STATUS A, B, C & D | What Do They Mean... - Constructandcommission.com (2024)

References

Top Articles
Latest Posts
Article information

Author: Velia Krajcik

Last Updated:

Views: 5912

Rating: 4.3 / 5 (54 voted)

Reviews: 93% of readers found this page helpful

Author information

Name: Velia Krajcik

Birthday: 1996-07-27

Address: 520 Balistreri Mount, South Armand, OR 60528

Phone: +466880739437

Job: Future Retail Associate

Hobby: Polo, Scouting, Worldbuilding, Cosplaying, Photography, Rowing, Nordic skating

Introduction: My name is Velia Krajcik, I am a handsome, clean, lucky, gleaming, magnificent, proud, glorious person who loves writing and wants to share my knowledge and understanding with you.